School buildings and the schools' other fights
Updated November 9, 2026
What's happening
The West Somerville Neighborhood School is whole again after three weeks of storm repairs. Pre-K through grade 4 went back to their original classrooms on Monday, November 2, and grades 5 through 8 rejoined them from the Tufts Administration Building on Wednesday, November 4. The district called it "a tremendous City-led team effort" of cleanup, restoration, painting and deep cleaning (SPS, Nov 4). In the October 11–12 storm, water got in through a roof drain partway through a re-roofing project and damaged about 10 classrooms plus breakout and storage rooms at the school, 177 Powder House Boulevard. Only one school day was lost, Ward 7 Councilor Emily Hardt wrote on October 26. Seventh and eighth graders moved to the Tufts building, 167 Holland Street, first, and grades 5 and 6 followed. An industrial hygienist found "no reason for concern" (Cambridge Somerville Independent, Oct 13). Our sources still don't say what the repairs cost or who pays, the roofing contractor or the city. The new five-year capital plan puts $3 million of free cash into the WSNS roof and $7 million of borrowing into its chiller (The capital plan: fix it first, borrow last).
Because the leak came mid-roofing, the October 22 Council agenda carried an order asking the administration to write or update a severe-weather protocol for construction and roof-repair projects. It covers checking that roof drains work, putting temporary protection in place and having staff ready to respond to water intrusion (Somerville Chamber of Commerce newsletter, Oct 22). Our capture has only the title, not the sponsor or the outcome.
The high school's terracotta is coming loose again, and the contractor is paying for the fix. Infrastructure and Asset Management Director Rich Raiche told the joint School Building Facilities and Maintenance Committee on October 6 that a staffer spotted a leaning tile under a library-side window sill. Envelope subcontractor Sunrise secured it within the hour and later took it down by boom lift. The tile had chipped where its metal clips hold it. The city's working theory is thermal expansion, since both failures came in September. The manufacturer, NBK, says chipping from that cause has never been recorded in its system (Oct 6 digest). Council President Lance Davis's September 24 order (26-1452) asks Raiche to present on "continued concerns" about the exterior tiles (Legistar).
The city and Sunrise have "agreed, in principle," Raiche said, that Sunrise will make L-shaped metal restraints at its own expense to hold the tiles where they end at the window sills. Installation runs past the first snow and into spring, with monitoring until then. The administration also plans to ask the Council for permission under the surveillance ordinance to inspect the facade by drone (Surveillance, police technology and AI). The item comes back in November.
The newest building complaint came from a fourth grader. On October 8 At-large Councilor Kristen Strezo filed two items on the bathrooms of the Winter Hill Innovation School, which is housed at the Edgerly. One covers all repairs, and the other a urinal students call "The Blaster" because it sprays toilet water. One boys' bathroom serves grades 1–5 on two floors, two stalls have no doors and two can't lock. Strezo asked that the items stay in committee with written timelines until parents and students confirm the work is done (Oct 8 digest).
The October 6 meeting closed three items:
- Argenziano: the district says the cafeteria balcony meets state and OSHA requirements.
- Edgerly: the temporary cafetorium AC "performed well" in September's heat. The permanent fix is still a transformer costing about $3 million.
- Kennedy playground: poured rubber is "the only surface" that meets safety and ADA rules, and it can't be shoveled. DPW has mapped hardscape at every elementary school that can be cleared for recess.
Districtwide, the state's independent review by the American Institutes for Research found strong foundations but uneven practice (SPS, Oct 6).
The story
Afterschool arts: a gap, not a cut
In early October some families were told of pending cuts to Music and Theater Arts afterschool programming. The city's October 9 eNewsletter called that "inaccurate information." The June budget raised the program's funding, but about 80% more students signed up this fall, which opened a gap. SPS says the gap will be covered and every enrolled student gets a spot. A joint statement from School Committee Chair Emily Ackman and Mayor Jake Wilson puts the raise at $14,600 more for teacher stipends, "an increase of nearly 50% from FY26" (Somerville Times, Oct 12).
The teen center: from Cummings to the high school
The 1931 Cummings School was the School Committee's candidate for a teen center. Raiche's September 1 memo priced a full renovation at $28,295,541. Prescott-wing offices alone came to $13,217,746, and he recommended leaving both out of the capital plan. At-large Councilor Jonathan Link: "hiring extra staff has to be cheaper than $28,000,000" for after-hours space at the high school (Sept. 8 digest). On October 20 Finance kept the resulting memo request (26-1427) in committee. Wilson and Superintendent Rubén Carmona plan to walk the high school first, and the administration hopes to pilot a teen space "very soon" (The capital plan: fix it first, borrow last). Cummings keeps its winter job as the warming center.
Kennedy: mold, then a $3M schoolyard
In April the Kennedy PTA asked for an air-quality plan, citing wet ceiling tiles and "more visible mold." DPW Commissioner Eric Weisman conceded the city had no process for mold complaints (April 30 digest). Complaints now go through 311 to a DPW investigation. The Council approved $3 million for the schoolyard on Feb. 26. The parking lot and stormwater work went in this summer, and the playground follows next summer.
Edgerly: swing space at its electrical limit
The Edgerly Education Center, where most displaced Winter Hill students go, overheats. The permanent fix is about $3 million for a new Eversource transformer and panel upgrades. It's a long-lead item that likely can't go in before summer 2028. Raiche wants it in the five-year plan because Edgerly is the "vital classroom swing space" for future East, West, Kennedy and Healey work.
Argenziano, Healey and East Somerville
The Argenziano's boilers are being replaced with $500,000 in free cash approved June 11. The new capital plan also funds Argenziano boiler work, plus cafeteria, HVAC and roof work at the Healey (The capital plan: fix it first, borrow last). Weisman's March staffing analysis made East Somerville the outlier, with 738 students and one daytime custodian (March 23 digest). No position was added in FY27.
East Somerville's facade is in the capital plan and already out to bid. IFB 27-17, East Somerville Community School Facade Stabilization, was released September 23. It held a pre-bid site visit September 30 and posted an addendum, and it required a 5% bid deposit. Filed sub-bids were due October 8 and general bids October 15 (city bid page). The bidders and price aren't in our sources yet.
The school resource officer question
The School Committee ended the full-time School Resource Officer program at the high school. On June 4 Carmona said an off-site Student Liaison Officer model "remains on the table." No memorandum of understanding has been signed (June 4 digest; Civilian police oversight).
What's next
- Done November 4: all WSNS grades back in their own building. The repair cost and the severe-weather protocol order are still open.
- October 15, 2026 (passed): general bids opened on the East Somerville facade stabilization, IFB 27-17 (outcome not in our sources yet).
- October 2026: Wilson and Carmona's walk of the high school for a teen-center pilot (outcome not in our sources yet).
- Done in October: the MSBA board moved the 925-seat Winter Hill and Brown replacement into schematic design; forum November 10 (The new school at 115 Sycamore Street).
- November 2026: the high school tile item, including Davis's order (26-1452), returns to School Building Facilities and Maintenance; the Council's hearing on the capital plan (The capital plan: fix it first, borrow last).
- Pending in committee: the Winter Hill bathroom repairs, with written timelines; the teen-center cost memo (26-1427); the severe-weather protocol order.
- Coming: the administration's surveillance-ordinance request to inspect the high school facade by drone.
- January 2027: MSBA Accelerated Repair Program applications open; School Committee member Laura Pitone wants the city to apply, with the East School facade as a candidate.
- Spring 2027: Sunrise's tile restraints finished. Summer 2027: the Kennedy playground. Summer 2028 at the earliest: the Edgerly transformer.